I'd like to change the status in which the Jira Burndown chart uses to consider a story as resolved.
So, instead of accounting less X points when a story went to Done Status, it would count when it goes into a diffrrent one. Is that possible?
We only do deployments in the end of the sprint over here (for now), so my Burndown chart basically only gets updated at the last day of the sprint, when all the Jira tickets go to Done status.
We use the 'Ready to Deploy' status once a story is done (only missing deployment), however it's a 'blue status', so the Burndown chart doesn't take it into account.
I know I can turn that 'Ready to Deploy' status into a 'green status', however was wondering if I could reconfigure the settings of the Chart to work differently by chance.