I have 2 boards, one board - I have access to the Timeline and can create Epics/add tasks to it. The OTHER board - I do not have access to the Timeline. How do I get access to the Timeline for my 2nd board?
Thanks!
Hello @Brooke Piegat
The Timeline feature will be available only when the underlying board filter is structured to explicitly reference one and only one project.
That means the filter must include:
project=X
The filter can have other criteria joined to the above with an AND operator.
If the board filter generates a scope that includes more than one project then the Timeline feature will not be available.
Since you have a Premium subscription you could look at using the Advanced Roadmaps Plans feature to create a timeline for that board.
https://support.atlassian.com/jira-software-cloud/docs/plan-and-view-cross-project-work-with-advanced-roadmaps/