I'm trying to add a column for Risk to highlight the projects which are at risk as deadline is nearing and they are not meeting 75% completion criteria.
So we have quarterly projects, considering 33% plus completion is not at risk for the 1st month and similarly 66% completion for 2nd month and same as 75% and above for third month.
I'm trying to implement a simple formula of putting above scenario in the last month of quarter using this formula.
if Progress < 75% then "Risk" else "Not at Risk"
however I'm getting an error.