Working in JIRA Cloud, Company-Managed, Classic Project. I'm experiencing a few issues regarding the estimate bubbles in the backlog and I'm not sure if there is a settings issue (user error) or if things are simply working as intended.
Issue #1
For some reason, the Not Started value always appears as zero. Should it not be showing a Story point total for all Cards not in progress (To Do column with Status of Not Started)?

#2
The In Progress value always shows the total number of story points in the release for all cards that are not in one of the completed statuses (Done, Cancelled, etc). Meaning it shows total value for cards in In Progress, as well as the To Do/Not Started cards.
#3
The Completed value will always show the total number of story points completed for the release but only for user Story cards. It does not include the points completed for planned Bugs which we also assign Story points to.
Any help or suggestions are appreciated!