We are a school portrait company. Before "Picture Day" there are steps that need to be completed. These steps have deadlines relative to the main date (get student info 1 week early, prepare forms the day before, complete and deliver orders within two weeks). I'd like to set these up with a planned date for next year. When the Picture Day is scheduled, all of the related tasks should be moved appropriately.
Is there a way to do this? I would also want to have this saved as a template so that we don't have to create all of the tasks for each school we serve every year.