Summary
Hi! As a Project manager on one of products, I have spotted an issue, when Jira thinks that there's no time left for the task but according to the estimation it's at least a third of it
Here's more clear specs:
- Application: Jira software
- Project type: Software
- Managing type: company managed
- Sprints: enabled
- Advanced roadmaps: in use
- Estimation type: original time estimate
Ticket info:
- Ticket type: bug
- Start date: 15 Nov 2023
- Estimation: 8 hours
- Time left: 3.67 hours
- Jira's value: 100%, 0 of 3.67 hours remaining
- Current state date: 16 Nov 2023
Some screenshots


Question:
Having checked all the values that affect the estimation and timeline, either what am I missing or does Jira really has an issue with placing tickets on a timeline?
Thanks in advance!