I cannot complete the sprint, because warning says i have 17 open issues, but i have already mark that 17 issues with status that mark the resolution to "done"

17 open issues, but i have all resolution to "done"

Filter only "task" and "story" within sprint-3, a total of 17 issue

Filter for all Sub-task within that "story" and sprint-3 , but for the total of sub-task is 57, no match for 41 completed issue or even 17 open issues.

i just tested add another issue on backlog without attach it to sprint-3, and i change the status from to-do to RC Deployment, when status in to-do. the "complete" sprint from sprint-3 still only have 41 complete issue. but then after i change status to rc deployment, the "complete" screen page from sprint-3 change to 42 complete issues.
so the sprint 3 complete issues too acting funny because it may look-like related to issues on backlog