Our tickets work as follows:
Project Parent Ticket
- Sub-Task 1 (In Progress)
- Sub-Task 2 (Backlog)
- Sub-Task 3 (Backlog)
- Sub-Task 4 (Backlog)
- Sub-Task 5 (Backlog)
We need to mark Sub-Task 1 as resolved and then only start with Sub-Task 2. Currently, there's no dependency between the Sub Tasks. What I want to do is use specific fields like scheduled to start, Solution Completed, ,Assigned, Status from the previous sub-task in the current sub-task. This will give me an indication of when the next Sub Task will start as its grouped by Status into seperate widgets and backlog items are not assigned.
So, I would like to see this:
Project Parent Ticket
- Sub-Task 1 (In Progress) - to finish 10/11/2023 - 55% Completed - Jimmy
- Sub-Task 2 (Backlog) - to Start 11/11/2023 - Prev Task 55% Completed - Jimmy
- Sub-Task 3 (Backlog) - Empty Start - Prev Task 0% Completed - Not Assigned
- Sub-Task 4 (Backlog) - Empty Start - Prev Task 0% Completed - Not Assigned
- Sub-Task 5 (Backlog) - Empty Start - Prev Task 0% Completed - Not Assigned
All the information can be inserted into the notes section or concatenated into a seperate field. The trigger will be a schedule every day but I'm not sure how to say "Sub task 2 should look at Sub Task 1 and get those details. Then Sub Task 3 should look at Sub Task 2" etc. I'm assuming it will be some JQL somehow in the Automation but not sure how to set this up and if its possible.