Hi All -
I have a variation of the fairly common question of using automation to copy sprint start/end dates to "Start Date and "Due Date".
My issue is not with the copy itself. That works fine. What I am running into is if an issue spills over to an additional sprint, the automation runs, and it copies the dates (again) from the Original Sprint.
Has anyone worked out a solution for this?