As the project manager, I'm exploring ways to prevent others from changing the initial task estimates while still allowing the logging of hours. Any suggestions or solutions would be appreciated.
Hi @Zainab Hassan
I think you can remove the time tracking field from the Edit screen and just leave it on the View screen and then you can add a transition screen with the Time Tracking field and set a condition for the transition and allow only users that you want to edit the original estimation.
The transition can point to the same status so it won't change.
It looks like you're new here. Sign in or register to get started.