Hi
Our company is starting to use Structure to manage a large cross-team project. Multiple teams, multiple Jira Projects, and a mix of Kanban and Scrum (another question incoming about that!).
We've made some progress in getting a Structure set up, but one thing that would be useful would be to be able to set a start date and a target end date for the project and be able to see percentage of time elapsed. This would enable us to use the Progress as measured in the percentage of tickets/stories/points that we have at the moment, and compare it with time passed. For example, we might see that we've done 67% of stories, however 80% of possible time has already passed, and we know that (potentially...) we're pretty behind where we should be.
Has anyone done this already that could share any solutions?
Cheers!