Hi community,
We are trying to define automation metrics for projects in Jira Cloud and Confluence and I got stucked wih some fields.
We are trying to implement this automation to track the timing of projects. So we have created a custom field named "Time" with three colored fields (yellow, green, red) which will be automatically changed depending on the due date and the field work ratio. However, the work ratio cannot be used in the automation.
Any idea of how can we track the timing taking into account we need the due date and the progress of the issue?
| due >= “14d” | due <= “-14d” | due <= “0” |
Work ratio > 100% | yellow | yellow | yellow |
Work ratio = 100% | green | green | green |
Work ratio > 81% AND Work ratio < 99% | green | yellow | red |
Work ratio > 61% AND Work ratio < 80% | green | red | red |
Work ratio > 41% AND Work ratio < 60% | green | red | red |
Work ratio > 26% AND Work ratio < 40% | green | red | red |
Work ratio > 1% AND Work ratio < 25% | green | red | red |
Work ratio = 0% | green | red | red |
We have two numbered custom fields (estimated CAPEX and actual CAPEX) which is manually updtaed by the Project Managers. As in the previous problem, we've created a new custom field named "Budget" with the three colored options which would be automatically changed by the difference of both fields. As well, this automaiton cannot be done by automation.
Budget is green if "CAPEX (real)" < "CAPEX"
Budget is yellow if"CAPEX (real)" = "CAPEX"
Budget is red if "CAPEX (real)" > "CAPEX"
Any idea of how can we track the difference of estimated and real CAPEX on this?
Many thanks in advance!
Anna