Is there a way to get the sum of the Original Estimates of all sub-tasks planned into a Sprint?
The reason for this:
We do 'Capacity Driven Sprint Planning'
We estimate our Backlog Items (e.g. Stories) in Story Points
We then break down the Stories into sub-tasks and estimate those sub-tasks in time.
Our 'Capacity Driven Sprint Planning' technique then finds the availability of each team member for the Sprint (e.g. assume 1-week Sprints for simplicity and assume 3 Developers on the team: Developer A has 30h availability, Developer B = 30h, Developer C = 20h)
So total team capacity for the 3 Developers = 30+30+20 = 80h
And so it would be nice to cross-reference the Developers' total capacity with the sum of all the Original Estimate on all sub-tasks, just to confirm 'the work will fit'