Hello,
In our Jira setup we had multiple Story Points custom fields. To reduce complexity, we removed all duplicated Story Points and migrated all values to a unique Story Points field. After the migration, redundant Story Points custom fields have been deleted from Jira.
Problem:
Velocity chart in a project that used one of the removed redundant Story Points fields doesn't show historic data (but only for the latest sprint since the team started using the unique Story Points field). Looking at tickets, they all contain this information in the unique field. Did anyone face with a similar situation? How can I "make" Velocity chart properly read value from the unique Story Points and display data for past sprints?
Many thanks in advance!
Best,
ds
P.S. I've already selected the unique Story Points field for estimates in the board setting page.