In Advanced Roadmap, is it possible to estimate the completion date of an Epic based on tickets time estimates and dependencies?
Thank you very much,
Hi @Frédéric Boisvert
Welcome to the community..
No this is only feasible you can roll-up by estimation and dates.
Not combined and not by dependency.