Hi
I am currently testing Jira Software Advanced Roadmaps in context of a project portfolio of a digital transformation projects. With the main goal to gain visibility on the resource consumption overall.
There is one thing I still struggle with: When assigning the estimated workload in hours, Advanced Roadmaps fully books available capacity of a team assigned on the next possible slots. Which, of course, in principle is useful as it indicates when you work on your projects in sequential mode. But as we got many resources, involved in different projects simultaneously, i we would rather prefer to have the workload of one issue, planned within a certain timeframe, split equally on all available weeks according to the portfolio planning. And allow to book the same resources on other, also equally distributed projects instead.
Any suggestions how to make advanced roadmaps change the split of workload from maximum available to distributed over project duration?
Thanks for any assistance and explanation.
Cheers
Peter