I need to update my workflow to if any one of my team try to transfere any issue to InProgress original estimate will be required.note : i was tried that but Original estimate field not found.
Hi @AlaaKassemSenousy , welcome to the community.
Original estimate is part of Time Tracking which also includes Remaining Estimate. Try using Time Tracking in a Validator on your transition(s) to In Progress.
Hi @AlaaKassemSenousy If you have properly set as the Filed Original Estimate is required in your validator in the Post function it should work.
Meanwhile check if other time tracking related fileds are available in the fields or not. We need to add the validator mentioning a filed "Original Estimate" as required.
I can't find TimeTracking or original estimate on the field. although i added them before for tasks ,bugs,and subtasks from project setting --issue types
@Jack Brickey
How can i do it please @Sanjog Sigdel
It looks like you're new here. Sign in or register to get started.