Looking for some suggestion on creation an automation or JQL to help move a subtask by the same number of days by which it's changed in the parent task.
For instance, due date on a Story is Aug 15, 2023, which gets changed to Aug 17, 2023. Then to move the due date on the Sub-task as well by two days irrespective of the due date, so for instance the due date on sub-task is Aug 12, 2023 that gets updated to Aug 14, 2023
Thanks for any suggestions and insights for this request.