Hi
Jira's default hierarchy for team-based soft project seems to be.
Epic -> User story - Sub-task
Our team wants to estimate sub-tasks using story points, and then we want to measure our velocity and sprint burn-down chart using subtasks.
Can we do that in Jira?
The default Sprint burn-down charts and velocity reports do not seem to consider sub-tasks which is really frustrating.
Any ideas or workaround?