Hi everyone,
I wanted to use the Plan functionality to show a full structure in Jira.
What I'm expecting is:
- Show the high level issue type and all its dependencies
Scenario:
- I have an issue type called 'program' which I'm linking as a "Parent link" to epics across different projects.
- I created a filter using the option "portfolioChildIssuesOf" so I can see epics across project linked to a parent issue
- I used that filter in the plan creation
- Somehow the plan shows only the Epics
- It doesn't display the Parent issue nor the child issues (taks and subtasks)
Is there any configuration that needs to be done to meet my expectations?