Hi guys
I have 2 issues that I would like you to help me with:
1. Our team is working with Original estimation. When we add subtasks to a story, and each subtask has its own Original time estimation, how can we reflect that on the story's Original estimation? (not manually but automatically sum the subtasks estimation and add it to the story Original estimation).
2. Second thing is the view of the Original time estimation + remaining time + issues num, per assignee in the backlog.
currently it doesn't show the correct Original time estimation, it doesn't include the estimation of the sub-tasks.
also, if a story for example has a time estimation of 2 days and assigned to person A, but has sub-tasks that are assigned also to person B, then person A gets 2 days in the time estimation in the backlog, and person B gets 0 days.
now, this is wrong for our team, because we want to see it according to the sub-tasks. and if a story/task doesn't have the sub-tasks then according to the story/task time.