I am setting up my first Advanced Roadmap via Plans. I have added two projects as issue sources and then assigned those sources for the teams I am including in this view. Each of those teams works in 2-week sprints. We don't manual add start and due dates, so my goal here is to populate the dates based on sprint start/end dates. I have noticed though, that it's not working (as shown on the screenshot below).
However, if I change the issue source to board, not project, then the timeline information is populated.
Could someone clarify whether this is the correct behaviour? Meaning when I use projects as issue sources, I won't get the start/due date auto-populated based on my sprints?
Thank you!