Hello,
At the end of a sprint, available with the plugin Scrum, I should close it.
Normally, all the open tasks are send to the next one. But not the "done" ones.
But since 2 or 3 weeks (sprint) it seems that the status "Done" is not recognize as a "final" status anymore when closing a sprint. All my done tasks / story / bug, are automatically associated to the next sprint with the same status "done" ( highlighted in green and id striked )
I checked in the workflow and the status "done" is Green and defined as a final status.
I recently added a second final status "Obsolete" , that could be the reason why it doens't work properly anymore, but in the workflow, nothing presume that we connot have 2 final status !
Do you have any clue ?