Hello everybody!
We have three Scrum teams in our programme, each of which has its own 'team' using a custom field in Jira.
Teams are linking dependent Issues using the 'has to be done before' and 'has to be done after' relationships.
I'm not worried about about dependent issues where both giving and receiving issues are in the same team (e.g. Issue '2' is dependent on Issue '1' but both Issues belong to Team 'A') - those relationships are dealt with at the team level.
I'd specifically like to be able to see a report that returns only instances of cross-team dependencies - i.e. where one team has a dependency on an issue in another team (e.g. Team 'A' needs complete Issue 1 before Team 'B' can complete Issue '2').
Any way to do this natively in Jira and / or with some sort of plug in?