This is question for Jira Data Center and Server 8.2. Does anyone definitively know the answers to these Velocity Chart report logic questions?
1. If a story/points are pulled into a sprint after sprint start, are the points committed?
2. If the sprint starts without any stories/points, are there 0 points committed? Will pulling in a story after sprint start commit points to it?
3. If a story/points are completed after sprint end, which sprint will the points be counted?
4. If points are counted in a past or closed sprint, will that reflect in the velocity report immediately?
5. What status must the story/points be in to be "completed" at sprint end: Done or Accepted?