Hi, is there any way to display the start and due dates on the schedule bar in timeline view? Many thanks
Hello @David Sagyibo
Welcome to the Atlassian community.
If you hover the mouse pointer over the bar the dates will display.
What problem are you trying to solve by have the dates fixed in the display?
Hello @Trudy P Claspill , many thanks for the quick feedback. What I would really need is to export the timeline/Gantt chart with the dates displayed in order to put it in our regular status meeting presentations. Our stakeholders requested this for them to be able to have a more accurate view on tracking each issue.
It doesn't look like that the native functionality for Basic Roadmaps/Timeline will support what you want.
So far I have not found a change request for this for the Basic Roadmaps functionality.
You might be able to find a third party Gantt chart app that would provide the functionality, in the Atlassian Marketplace.
Hi @Trudy P Claspill ,
Many thanks for coming back to me - as per your advice I'll check other Gantt chart options for this purpose.
Cheers, David