We are evaluating JIRA Project Management for a client purpose (whether it can generate portfolio level reports, track resources, timelines and budget etc.)
Key requirements are -
- Creating baseline project plan (once committed, this should not be allowed to change)
- Generating alerts if any dates change from baseline plan (maintain versions of baselines)
- Tracking timelines at portfolio level
- Allocate resources and create a resource utilization view across the portfolio
- Allocate budget and maintain planned v/s actual numbers (both need to be inputted manually for now)
Looking for some help if this can be done in JIRA?