Is it possible to reset estimation/velocity when there is a major team change? Would disabling board estimation and then enabling it reset the velocity calculation? We have just restructured our team and the size of the team is significantly smaller than it was. The velocity of the larger team is still being used in reports when in reality the velocity of the new team needs to be re-established over the next few sprints and will be significantly different than the prior sprint velocities.
Is there a Jira best practice for managing velocity following major team changes?