Hi all!
Is it possible for all sub-tasks to inherit the Sprint of their parent AND
If the Sprint of their parent changes, update to stay aligned to their parent?
Thanks!
Hello @Adam Taylor
The core functionality of Jira Software is designed so that Sub-tasks automatically inherit the Sprint of their parent issue, because Sub-tasks cannot be assigned to sprints separately from their parent issue. You don't have to do anything extra to make that inheritance happen.