Hi all,
I'm stuck with the following problem.
Intention is to create sub-task

and copy certain fields content from parent task to sub-tasks.
As long as task as well as sub-task are in status in progress this works;
but not in status backlog.

I can create a sub-task when task is in backlog but field content will not be copied to sub-task, although both status have same conditions etc.
Condition and postfunction of transition 1 and 2 are:


I gave exactly the same condition and postfunction to backlog transitions (3). But it only works in the moment both (task and sub-task) are in status in progress.
What haven't I considered?