Hi there
Hoping somebody might be able to guide me in the right direction as most of the articles i am finding don't appear to help and community posts i've come across are a few years old.
I am experimenting with a company managed scrum project and setting up sample Epics with associated Tasks. I see that irrespective of the Task start and due dates, the Gantt chart shows their dates as the length of the sprint. The setting for Child level issue scheduling is enabled. Is there a way to separate the sprint from the Task dates to better reflect each Task in the Gantt view without using a team managed project and disabling the sprint/backlog features?
This article appears to reference "Schedule child issues by dates" but i don't see this option in either company or team managed projects.
https://support.atlassian.com/jira-software-cloud/docs/enable-child-issue-planning-for-kanban-teams-on-the-roadmap/
Thanks