I have the status in the task "Rejected" with the corresponding resolutions "will not be executed" and so on - the status is the same as "Closed". The main task is "Closed". But I cannot close the sprint.
Hi @Ivan Andrieiev ,
please put Rejected status to the last column on the right in your scrum board settings.
This should fix your issue.
Fabio
Hello @Ivan Andrieiev
Only the issues in the column farthest to the right on your scrum board are considered "complete" when closing a Sprint. It does not matter what the actual Status value is. The Status values for all items you want to be considered "complete" need to be mapped to the right-most column as @Fabio Racobaldo _Catworkx_ suggests.
@Trudy P Claspill and @Fabio Racobaldo _Catworkx_
this of course has little logic, but thank you.