I have just started a new sprint (sprint 3), which already has tickets in the backlog, ready to go.
When I go to close the previous sprint (Sprint 2), Jira will only let me move tickets to sprint 4 and above, but I need them to into the current/next sprint (sprint 3)
Why is this happening and how do I fix it? Why doesn't sprint 3 show up in the dropdown menu to move sprint 2 tickets to?
I have tried editing sprint 3 to start later in the day, this doesn't help. I also can't delete it because that will mess up the whole roadmap. It looks like my only option is to manually copy tickets into Sprint 3 before I close Sprint 2?