I am using a Kanban board and I have the following columns in it:
- Open
- Triaged
- In progress
- Resolved
When we analyze the ticket, we decide on its rank (i.e. where exactly in the Triaged column it should sit). Lets say we decide that it should be 5th in the order of priority (i.e. rank) in the Triaged column, so we take the ticket, drag it from the Open column and drop it into the Triaged column.
The problem is that when dropping, we are not able to select to drop it exactly between, for example, tickets 5 and 6, because Jira highlights the entire column without the reference of the tickets that are already in that column. So what happens is that we have to follow a 2 step process - first drag from Open and drop into Triaged column and then move inside of the Triaged column to place the ticket in the respective order (e.g. 5th).
Can anyone tell me how to do it in one go/action?