I was created 5 Deferent issues I seen some 3 issues have create subtask option remaining tasks I didn't find any create sub-task in these 2 issues.
how to enable this in remaining issues.
Hi @Vishnu Vardhan Chenna
Do you mean that for the same base/standard issue type in a project, some issues allow you to create sub-tasks and others don't?
If a/the sub-task issue type has been added to the issue type scheme associated with the project, you should always be able to create a sub-task for any of the base/standard issue types in the project.
You also need the permission to create issues in the project. But it is usually what Dave says - there are no sub-task types configured for the project, or your issue already is a sub-task.