My team and I are using the swimlane feature set to 'stories' to show different swimlanes for each story that has sub-tasks; very useful. However, what is a shame, is that once the sub-tasks in the story are moved to done, then there is nothing to move on the kanban that represents the story as a whole.
Is there a way to have the story still show up on the kanban e.g. in the 'other' section as well as a swimlane?
Obviously as a work around, I could have a placeholder ticket that represents the final steps required to close out the story as a separate sub-task, but I am not a fan of likely duplicating info that is already in the story.