Hi all,
Our Way of Working is to have User Stories with Tasks linked to it, not sub-tasks. I want an automation rule that works only when all Tasks that are linked to the User Story as "blocks" are closed, but if there are other Tasks linked to the User Story *not* as blocking the User Story (ex: relates to, depends on, etc) then those Tasks when marked Done will not transition the User Story to Done.
This is the rule I've written, but it will close the User Story if a linked Task "relates to" is closed to Done. What do I need to change?