I have several tasks. They all have blocked by links to various user stories.
I want to convert these tasks to subtasks with their parents being the linked issue in the task.
How do I do this?
--
Steps I've taken so far
- Created a filter to get all my issues that are task in a specific project. Its almost 200 issues.
- clicked on the 3 dots for bulk change
- clicked on all issues then next
- selected move issues. I cant use edit issues because i cant edit the issue type to subtask.
- kept the to project the same as source.
- changed task to subtask.
I need to fill in something for Select Parent Issue.