I have a Kanban board that lists Epics how do i get the tasks within the epic to show and appear in the swim lane based on the status they are in?
Hi @Trena Norcia,
Assuming you are using a kanban board in company managed project - the issues on the board are selected from the board filter, which you can retrieve and edit from your Board Settings > General > Saved Filter
If you want to see both your epics and tasks, you must ensure that the tasks linked to your epics are also retrieved with that filter.
Once you've done that, you can navigate to Board Settings > Swimlanes and select Epics as the element to base your swimlanes on. That should create a swimlane on your board for each Epic with the linked tasks underneath.
Hope this helps!
It looks like you're new here. Sign in or register to get started.