Hi Everyone
I have a Query:
I have a ticket under an Epic. The ticket has 30 days of work estimated. In the roadmap I cannot draw the timeline of 30 days for this ticket. This ticket is assigned to a sprint of 10 days. The JIRA roadmap shows only the timeline as 10 days for this ticket since it is assigned to a sprint of 10 days length.
I can only change the timeline of the epic manually.
Can I show the timeline as 30 days for this ticket under epic in Roadmap??