I set up a "Plan" to run a cross functional project. I created an Initiative and linked all my epics to it. Then I created a filter using "Parent Link" in (My Initiative, My Epic 1, My Epic 2). I had my plan use this filter as a date source and it worked.
My only question remaining, is when I look at my Plan, the very first line says "2 issues without parent". This does not make sense to me and the two issues are epics and I have linked these two epics to my Initiative. Is there any way to fix this. Thank you!