how to run an automation rule to clone one specific task?
Hi @Ivan Andrieiev
We need more information, as always. :-)
What is the task? How are you identifying it?
Quick answer is that you would add a Condition or a Branch to identify the task, and then add a new action after that to Clone Issue.
Hi @Ivan Andrieiev,
Create an automation rule with a manual trigger. As automation action, select clone issue and define the fields you want to copy.
You should be able to trigger that rule from an issue, by selecting the Automation rules link in the details panel of an issue you open.
Hope this helps!
You could do this using a Scheduled Trigger
You have two options in terms of creating the Task:
Is the Task you're cloning one specific Task? Or is there some other logic to identify it? I've assumed it's one specific Task below.
---
Option 1 - Clone Task
Option 2 - Create New Task
Let us know if either of these work for you!
Ste
@Walter Buggenhout @John Funk
There is one specific task that needs to be done every day. I know how to completely clone for tasks due to status change. But you need to do this action for one separate task. Identification is mainly based on the name of the task.
@Ivan Andrieiev,
You are basically saying that you want to create a recurring task that needs to be generated every single day. That was not really clear from your initial question, but if that's what you need, a scheduled solution as offered by @Ste Wright here should be able to deliver what you need.
Are you creating the task everyday no matter what happens to the task the day before? Or are you only creating the new task when the first task gets finished?
If you are creating it no matter what, then create a rule with a Scheduled Trigger. It should be fairly easy to do.
@Ste Wright
In second variant I have mistake
In Option 2 you're seeing that warning? Not Option 1?
Have you got JQL set in Option 2? If yes, what is it?
Perhaps provide a screenshot of the Scheduled Trigger so we can review further
I cannot understand this JQL, this line triggers the creation of a task according to the corresponding filter, if the JQL filter is executed only for one created task, then only one task is created, the JQL feature is valid for 25 completed tasks, then 25 tasks will be created?ExampleJQL priorities = MediumThere are 25 tasks in the project, so automation will do 25 tasks?