Have automations that run every week. However we sometimes need to change when the schedule time is. For instance:
Orginal Automation:
Automation Created : 11/25
When Scheduled: Every 2 Weeks @ 8AM
(This then shows the next 10 runs as 11/28, 12/12, 12/26, etc...)
This is where my problem comes.
They don't match up with when I would like this to actually start.
The date I would like the first run to happen 12/5 then every 2 weeks from then.
How do I change this date other than creating a new automation on that week?