How do I add holidays so that my SLA is not breached.
Hi @Swapnil Jayant Joshi
Go to your existing calendar and edit it.
There you see the holidays where you can add new or import ics holidays.
@Swapnil Jayant Joshi -
Welcome to the community. You will have to go to each of your JSM project's Project settings >> SLA section and adjust the calendar(s) that you use for your projects to add in the holidays as needed.
Hope this helps.
Best, Joseph Chung Yin
Jira/JSM Functional Lead, Global Infrastructure Applications Team
Viasat Inc.
Hi @Swapnil Jayant Joshi ,
you create a Calendar and define "non-working" days. Then you associate this calendar with your SLAs. Do you see this in your SLA screen?
create-a-new-calendar
careful with editing existing calendar if it is used elsewhere.
thank you.