Hi,
Is it possible for tasks on the advanced roadmap to move automatically in time by themselves when the task blocking them has not yet been completed?
Best,
Adrian
Hi @Adrian Bogacz
You could probably use Jira Cloud Automation for this.
Advanced Roadmaps utilises data from Jira - so for example if...
Then you could change Issue B's due date to be 7 business days later.
For example, the rule might be...
---
^ Let us know if you have any other questions