How to change the color of timeline/phases, If the due date is passed.
As the due date is passed it should change it to Red color.
EG: Task A have passed due date, it should be highlighted in Red color.
Hi @[deleted], thanks for your question.
I don't think this will be possible in a Jira Work Management project.
In a Jira software project, you can define the color / highlighting with JQL, like this -
and then in the board, you can get this highlighting here -
Otherwise, you can look for apps to help with this, but there will most likely be a cost associated with this - Explore apps for Atlassian products | Atlassian Marketplace
It looks like you're new here. Sign in or register to get started.