Hi there,
I know I can set a workflow condition to prevent a transition if sub-tasks are not in the state of DONE.
Is there something similar for linked issues?
I have a request that when approved created a linked procurement issue.
The main issue (the triggering issue) can be resolved or cancelled though and the linked issue could still be in progress. I couldn't see a transition condition to add for that and was wondering how people would handle this scenario?
Thanks