When scheduling work, JIRA Portfolio attempts to pull stories into a sprint until the team's capacity is "full". If the team has a small amount of available story points, Portfolio will pull tasks in from future projects.This can have the unfortunate effect of having the team appear to be starting a much later project WAYYYY before that will actually happen.
What I would prefer is for Portfolio to schedule the next story even if capacity indicates that the story won't complete in a single sprint. This much more closely reflects reality for my team.
My question of course: "Is this possible"?