Our project has a customed defined hierarchy of
Initiatives to Capabilities to Epics to Stories
Story Progress is easy not done = 0%; status DONE = 100%
Epic Progress = (Sum of Child Story Pts DONE) / (Sum of Child Story Pts)
Capability Progress = (Sum of [Child Epic Job Sizes * Child Epic Progress] / (Sum of Child Epic Job Sizes)
However I don't know how to set up a formula to do conditional weighted sums using the EXPR language for the Structure.
Can anyone point me to how this can be done, or a real reference document for this kind of detail for the EXPR language?