Hi all,
Hoping to find help for how to write an automation rule that will update a User Story's Start Date field when a linked Task's status is transitioned to "In Progress".
High level flow of how we work: our group manages updates to websites.
1. Epic - one Epic to represent the scope of the project (that scope could be updating just one page on the site, or it could be for building a brand-new site). Any associated tickets related to the project are linked to the Epic.
2. User Story - we break work down into a per-page basis, and sometimes smaller components that are global to all pages of the site. We use User Stories as a sort of "container" to which we link Tasks (not sub-tasks)
3. Task - we use Task, not sub-task, for each stakeholder. Most importantly, each User Story will have at least a developer-specific Task and a QA-specific Task so they can track their effort for the work via the Story Points field
Right or wrong, this is our WoW upon which PowerBI reports are generated for all sorts of metrics.
We now have a requirement to track the Start Date of a web page (or User Story), which is accomplished through updating the Start Date field in the User Story. The trigger for that is based on when the Developer updates their linked Task from "To Do" to "In Progress".
How can we write an automatic rule (not manual trigger rule) that will (here's the rule in plain words):
When a developer-specific Task is transitioned from "To Do" to "In Progress" then find the User Story that is linked to that Task and update that User Story's Start Date field with the current date.
If it matters, all issues associated with the Epic use the same Epic Link and Fix Version, and I have many rules set up with Labels (ex: the developer-specific Task has a unique label, same for QA and so on).